Assured AI programme: record and escalate a dependency
Process_AAI_Dependency · strict · 5 step(s)
A dependency starts as a native “blocked by” link in the workstream (req:aai-dependencies#DEP-01). It becomes a D-number issue in aai-programme only when it is programme-significant: it crosses workstreams or partners and needs a deadline, negotiation, escalation or an assessment of consequences (req:aai-dependencies#DEP-02).
How it connects
- Called by: no call activity names this process
- Calls: none
- Presented on: no docs page section shows this diagram
Lanes — who acts
| lane | role | what it does here |
|---|---|---|
| Workstream team | workstream-team |
The people delivering a workstream’s features, stories and spikes, in its own repository. |
| Workstream lead | workstream-lead |
Owns the workstream’s delivery and its project (req:aai-design-principles#DP-02). Proposes epics; never creates them. |
| PM & Architecture Integration | pm-architecture-integration |
Owns sequencing, dates, dependencies, evidence and escalation. Does not make technical readiness judgements (req:aai-design-principles#DP-05). |
Steps
Every one of the 5 step(s) is documented.
| step | lane | skill / sub-process | what it does |
|---|---|---|---|
Link the issues with “blocked by”A_Native |
Workstream team | — | GitHub’s native relationship between the two issues (req:aai-dependencies#DEP-01). |
Raise it with the PMA_Raise |
Workstream lead | — | Name the waiting epic, what it waits on, when it is needed by and the consequence if late. |
Create the D-number issueA_DNumber |
PM & Architecture Integration | — | In aai-programme, its title starting with the D-number (req:aai-acceptance#AC-14), its body following the DEP-05 template, with Workstream (the waiting one), Target date (needed by), Delivery health, Risk category, Impact and assignee (req:aai-dependencies#DEP-05). |
Write the Next actionA_Next |
PM & Architecture Integration | — | When it is At risk or Blocked: what will happen, who will do it, and by when, in the issue body. It then shows in V9 and V10 (req:aai-views#V9, #V10). |
Link the two epics with “blocked by”A_EpicLink |
PM & Architecture Integration | — | Only for a true blocking dependency between epics (req:aai-dependencies#DEP-03). |
Decisions
Every one of the 2 decision(s) is documented.
| decision | what decides it | branches |
|---|---|---|
Programme-significant?GW_Significant |
Answered by the lead against DEP-02: does it cross workstreams or partners, and need a deadline, negotiation, escalation or an assessment of consequences? | no → Handled in the workstream yes → Raise it with the PM |
A true blocking dependency between epics?GW_Epic |
Answered by the PM (req:aai-dependencies#DEP-03): is it a true blocking dependency on another epic, rather than on a review, an external decision or a shared platform item? | no → Tracked in V9 and V10 yes → Link the two epics with “blocked by” |