Assured AI programme: build the GitHub set-up

Process_AAI_Build · strict · 12 step(s)

Build the shared programme project, its repositories and automations in the order section 13 of the programme requirements sets, stopping wherever a decision, a credential or a pilot test is missing. Nothing past pre-flight is created until the decisions for that step are confirmed, and nothing is bulk-imported until every pilot test passes.

BPMN diagram: Assured AI programme: build the GitHub set-up

How it connects

Lanes — who acts

lane role what it does here
PM & Architecture Integration pm-architecture-integration Owns sequencing, dates, dependencies, evidence and escalation. Does not make technical readiness judgements (req:aai-design-principles#DP-05).
WHO GitHub owner who-github-owner Answers the section 3 decisions and makes the organisation-level changes only an owner can make (req:aai-decisions#BD-05, #BD-08).
Build agent build-agent Builds what the decisions allow and stops where the requirements say to stop. Never invents users, teams, repositories, dates or field values.
Technical Integration Lead technical-integration-lead Confirms validation with a comment starting Validation confirmed: and the evidence (req:aai-design-principles#DP-05, req:aai-automation#AUTO-10).

Steps

Every one of the 12 step(s) is documented.

step lane skill / sub-process what it does
Step 1: pre-flight
A_Preflight
Build agent — Inspect the organisation read-only: issue types, issue fields and headroom, project field counts, projects, teams, repository policies, SSO or EMU, and permissions. Reuse compatible configuration; create nothing that duplicates it.
Answer the open BD decisions
A_Decide
WHO GitHub owner — BD-01a, BD-03a, BD-03b, BD-05, BD-06 and BD-08, each with its recommended default unless the owner says otherwise. The answers are recorded on the programme issue.
Step 2: create or reuse issue types and fields
A_OrgSetup
WHO GitHub owner — Create or reuse the section 5.1 issue types and the section 7.1 issue fields, and pin them as section 5.3 says. If issue fields cannot be used, apply the section 7.4 fallback and record it.
Step 3: repositories, roles and labels
A_Repos
Build agent — Create aai-programme and the two workstream repositories the pilot needs, public, with the BD-04 roles and the section 7.3 labels (req:aai-information#SEC-04).
Step 4: programme project and template
A_Projects
Build agent — Create the programme project with views V1 to V13 in the listed order (req:aai-views), and the workstream template from section 8.3.
Step 5: READMEs and directory
A_Readmes
Build agent — Write the READMEs (req:aai-acceptance#AC-10, req:aai-automation#AUTO-07) and create the pinned Workstream directory issue (req:aai-linking#LINK-01).
Step 6: automations AUTO-01 to AUTO-11
A_Automations
Build agent — Set up the automations (req:aai-automation). Every script reruns safely and has --dry-run. None makes a judgement (req:aai-automation#AUTO-05).
Step 7: the pilot
Call_Pilot
Build agent calls Assured AI programme: the pilot Build and test the section 12 pilot set; see the pilot process.
Provide the section 14 inputs
A_Inputs
PM & Architecture Integration — The epics CSV reviewed by each lead, the Gates output list, R1 to R7, the dependency register with anything section 6 keeps off GitHub removed, the directory details, and the needed GitHub usernames.
Step 8: bulk import and backfill
A_Import
Build agent — Import the inputs, leaving missing values empty and listing them, then run the AUTO-11 backfill.
Step 9: charts and acceptance checks
A_Charts
Build agent — Build charts M1 to M5 (req:aai-metrics), or record which cannot be built natively, and check AC-01 to AC-19 (req:aai-acceptance).
Step 10: build report
A_Report
Build agent — Hand back the section 16 report.

Decisions

Every one of the 3 decision(s) is documented.

decision what decides it branches
Decisions for the next step confirmed?
GW_Decided
Answered from the section 3 decision record (req:aai-decisions): is every decision that step 2 onward depends on confirmed? no sends the open ones to the owner. no → Answer the open BD decisions
yes → Step 2: create or reuse issue types and fields
Automation credentials in place?
GW_Creds
Answered by whether the BD-08 credentials exist as an organisation secret. no stops and reports exactly which permission is needed (req:aai-automation#AUTO-09). no → Stopped: credentials needed
yes → Step 6: automations AUTO-01 to AUTO-11
Every pilot test passed?
GW_Pilot
Answered by the pilot’s results (req:aai-pilot). no stops the build and reports the failure; there is no bulk import after a failed pilot. no → Stopped: a pilot test failed
yes → Provide the section 14 inputs